DAMAC Group wants to grow the planned capacity of its global data-centre portfolio to 10GW by the end of 2027, up from around 6GW today.

Founder and Chairman Hussain Sajwani set the target at Bloomberg Invest Dubai 2026, according to reports by TradeArabia, BusinessToday, and HiDubai. The 10GW is planned capacity, not operating capacity. Zawya carries the primary article.

Subscribe to our Newsletters for more Business Stories

Where the 6GW sits now

The current portfolio is about 6,000MW of planned capacity: roughly 1,000MW in the United States, 2,500MW in Europe, and 2,500MW in Asia.

The pipeline includes Thailand, Malaysia, the Philippines, Finland, Spain, Greece, Italy, Türkiye, and the US. Sajwani said the group plans to buy more land outside the US over the next 12 to 18 months. It’s also in serious negotiations for a large site in Australia and is looking to expand in the UK.

The US programme was already public. Sajwani reaffirmed DAMAC’s $20 billion commitment there, of which around $9 billion has been invested, and said he expects the US to remain the world’s largest data-centre market.

Big sites, liquid cooling, rising costs

DAMAC focuses on large data centres starting at around 100MW, relying mainly on liquid cooling for AI chips and high-density computing. For more on that technology, see Tbreak’s story on LG’s cooling system for AI data centres.

Costs are climbing. According to BusinessToday, Sajwani said development costs have risen about 30% and could rise another 20% to 30%. He named supply-chain constraints and delays in getting essential equipment as major challenges for the industry.

The nearer milestones

The data-centre arm is DAMAC Digital, known until June 2025 as EDGNEX Data Centers by DAMAC. It was founded in 2021 and began with a 12MW campus. DAMAC Digital says it already has operating capacity in Saudi Arabia and Thailand.

Its 6,000MW announcement gives dates that make the 10GW goal easier to test. DAMAC Digital says its landbank spans 13+ countries and 35+ planned sites. It targets more than 700MW of operational capacity across 14+ sites by Q1 2027, and 2GW by the end of Q1 2028.

The company says it broke ground on 10 new sites in the past five months. It has signed partnerships with five global hyperscalers and expects eight sites to be operational by the end of 2026. More than 90% of its data centres use liquid cooling designed for next-generation AI accelerators, including NVIDIA’s Vera Rubin platform.

According to HiDubai, Sajwani said he doesn’t see the AI boom as merely a bubble but as a long-term transformation, while acknowledging valuations could correct in the coming years. He called for faster AI investment while practical solutions are found for energy and water demand.

Sajwani has money on the line. He said his investments in OpenAI, SpaceX, and Anthropic have produced gains running into billions of dollars. The Anthropic stake, made less than two years ago, has returned gains comparable to about three decades of his earlier business activity.

What it means for the region

Sajwani says the bottlenecks are “land, power, regulation, financing and speed.” The International Energy Agency projects global data-centre electricity use could roughly double to about 945 TWh by 2030, with AI a key driver. Tbreak has covered one regional answer, Oman’s green hydrogen auction with data centres as the buyers.

Within the Gulf, DAMAC’s target sits alongside Saudi Arabia’s push, including the Aramco deal for 49% of HUMAIN, which targets 3GW by 2030. DAMAC’s plan differs in one respect: the new capacity is overseas, and no UAE site has been named. The first real test is the 700MW of operational capacity due by Q1 2027.